- Due by June 30, 2027•0/5 issues closed
Release 0.2 should have stable support for phasor-domain dynamics simulations.
Due by September 30, 2026•6/10 issues closedImplement support for co-simulations with DataBroker. GridKit `SystemModel` needs to have an option to operate as ZeroMQ server.
Overdue by 10 day(s)•Due by July 31, 2026•3/4 issues closedThis milestone represents the items needed to be completed before we can mark the ACTIVSg2000 case as fully complete.
No due date•11/11 issues closedThis milestone represents the items needed to be completed before we can mark the WECC 240 bus case as fully complete.
No due date•8/9 issues closed